Main testing equipment configuration for third level repair, installation, and testing qualifications
brief introduction
On December 1, 2017, the National Energy Administration made corresponding adjustments to the qualification equipment for power testing. The qualification equipment for testing in each province and region is the same, and some equipment that is not commonly used by power enterprises in actual work is omitted. A brief introduction to the new version of the construction equipment selection guide for the third level power facility license for installation (repair, testing) testing is provided.
Obtaining a third level installation (repair, testing) license, one can engage in the installation, maintenance, or testing activities of power facilities with voltage levels below 110 kV.
To learn about the application materials and filling specifications for the installation, maintenance, and testing of power facility licenses, you can click on "Application Specifications" to browse.
Alternative names: Level 3 Testing Instruments, Level 3 Testing Equipment, Testing Instruments and Equipment, Level 3 Testing Configuration Table, Level 3 Testing Equipment, Level 3 Testing Equipment Selection Table
configuration table
Test Level 3 Configuration Table
Serial Number
|
Name of machinery and equipment
|
unit
|
number | Specification and model | |
NO1
|
High voltage generating equipment
|
||||
1
|
DC high voltage generator
|
cover
|
1
|
DC:200kV/3mA
|
***
|
cover
|
1
|
DC:120kV/2mA
|
***
|
||
2
|
Power frequency withstand voltage test device
|
cover |
1
|
AC:10kVA/100kV
|
***
|
cover
|
1
|
AC:5kVA/50kV
|
***
|
||
3
|
Complete set of equipment for frequency conversion series resonance test
|
cover
|
1
|
500kVA/200kV/2.5A
30~300Hz |
***
|
4
|
Induction voltage withstand test device
|
cover
|
1
|
5kVA/360V
150Hz |
***
|
NO2
|
Electrical measuring instruments
|
||||
1
|
High voltage dielectric loss tester
|
tower
|
2
|
1、介质测量精度为1%
2、电容量精度为0.5% 3、抗干扰变频 |
***
|
2
|
Loop resistance tester
|
tower
|
2
|
DC:≥100A
|
***
|
3
|
Transformer volt ampere characteristic tester
|
tower
|
1
|
1100V/5A
|
***
|
4
|
Ground Resistance Tester
|
tower
|
1
|
Frequency difference method
|
***
|
5
|
Capacitance and inductance tester
|
tower
|
1
|
|
***
|
6
|
Grounding continuity tester
|
tower
|
1
|
DC:1A
|
***
|
7
|
Transformer DC resistance tester
|
tower
|
2
|
DC:≥10A
|
***
|
8
|
Transformer ratio tester
|
tower
|
1
|
Digital 0.5 level
|
***
|
9
|
Transformer winding deformation tester
|
tower
|
1
|
Frequency response method
|
***
|
10
|
Load tap changer tester
|
tower
|
1
|
I≧1A
|
***
|
11
|
Circuit breaker characteristic tester
|
tower
|
2
|
|
***
|
12
|
Zinc oxide lightning arrester resistive current tester
|
tower
|
1
|
|
***
|
13
|
Three phase relay protection tester
|
tower
|
2
|
Two sets of three-phase voltage and current each
|
***
|
14
|
Lightning strike counter calibrator
|
only
|
1
|
|
***
|
15
|
insulation resistance tester
|
tower
|
2
|
DC:0~5000V 200G(Ω)
short-circuit current≥3mA |
***
|
NO3
|
Oil and gas testing instruments
|
||||
1
|
SF6leak detector
|
tower
|
1
|
sensitivity1ppmv
|
***
|
2
|
SF6Gas micro water tester
|
tower
|
1
|
|
***
|
NO4
|
Common instruments and meters
|
||||
1
|
Megger
|
only
|
1
|
DC:2500V
|
***
|
2
|
Megger
|
only
|
1
|
DC:500V
|
***
|
3
|
Digital dual clamp phase voltmeter
|
only
|
1
|
measuring current1mA~5A
|
***
|
注:1. All national users who purchase our products enjoy free technical guidance, software upgrades, one-year warranty, and lifelong maintenance services.
2. For more product information, please enter the product center. Service Hotline: 027-85824876
qualified
Those who have obtained the third level testing license for the installation (repair, testing) of power facilities can engage in testing activities for power facilities with voltage levels below 110 kV. The applicant shall meet the following conditions:
1. Legal personality and well-established organizational structure
2. Registered capital and net assets of over 12 million yuan
3. Experience of conducting testing activities on lines and substations with a voltage of over 10 kV for more than 3 consecutive years
4. The technical director and safety director have more than 5 years of experience in power facility testing and management, and hold intermediate or higher technical qualifications in power related majors
5. More than 20 professional technical and economic management personnel, including more than 15 power related engineering and technical personnel
6. More than 10 electricians holding a network operation permit, including 3 or more high-voltage electricians and 6 or more special electricians
7. Establish a sound and effective safety production organization and system, conduct safety training in accordance with the law, and have at least 3 full-time safety supervisors
8. Fixed business premises with a total area of over 600 square meters, various professional laboratories, and testing equipment for testing power facilities with voltage levels above 110 kV
9. A sound system for managing technical archives